Jack and Slide Procedure:
- Transport moves load in line to final destination will be
- Jack up load to allow slide beams to be placed underneath unit
- Shore up both trailer and slide beam not to allow movement when lowering unit onto slide rails and rollers
- Lower unit onto slide beams and rollers
- Final placement of slide beams, pads, and shoring are in place and anchored down if necessary
- hydraulically push unit into place of final destination
- Jack unit up off slide beams
- Remove slide beams
- Lower unit into final destination
Note: Safety blocking may be used between processes for added insurance and safe keeping